Langdon, N.D expansion project

Aerial image of a grain facility,

The Langdon terminal expansion will add an 850,000-bushel steel bin and supporting conveyance, including a third conveyor. The expansion will allow the facility to receive three commodities at the same time, which supports an increase in permanent storage, improvement to commodity segregation and is expected to reduce reliance on temporary storage. Construction began in September 2026, with the expansion tentatively expected to be fully operational by August 2027


Project updates

October 30th, 2026

Construction crews have begun pouring concrete for the new bin flooring.

Langdon, North Dakota construction project update